industrial
Langage Power Station
Blast-track cleaning of concrete floors and chemical-resistant coating
- Contractor
- Kier Construction
- Location
- Plympton, Devon
- Sector
- industrial
Blast-track cleaning of large concrete floor areas at Langage Power Station, then sealed with a chemical-resistant paint coating to handle process spillage. Working alongside Kier Construction.
More work
Recent contracts.
Midas · North Devon
North Devon Leisure Centre
Steel-lined swimming pool blasted and repainted
Network Rail · Pontypridd, Wales
Pontypridd Railway Station
Blasting, hot metal spraying and painting of structural steelwork
Mike Barrow (owner) · Dartmouth, Devon
Dartmouth Castle Pleasure Boat
Inside and outside blast and recoat of a 27-metre pleasure boat
Similar job in the works?
Spec, drawings, even a sketch on the back of a delivery note — send it across.